IH 35W/IH 820 Interchange |
|
| • |
|
Initial phases of construction for the general purpose lanes will begin. |
|
| • |
|
Continued construction on the managed lane tie-ins from northbound and southbound IH 35W to eastbound IH 820. |
|
| • |
|
The continued relocation of utilities, the construction of retaining walls and the setting of beams for the IH 820/Beach St. improvements. |
|
| • |
|
Note: The on-ramp from Meacham Blvd. to northbound IH 35W was closed on December 4. Project partners worked together to design and install a temporary on-ramp, which opened on December 21. |
|
|
IH 820 btwn Beach St and Denton Highway 377 |
|
| • |
|
Utility relocations and continued construction of the general purpose lanes. |
|
| • |
|
Continued construction of drill shafts and columns for the new Haltom Rd. bridge. |
|
| • |
|
Note: A traffic shift of eastbound IH 820 traffic to new pavement was completed in late January and will be in place for approximately six months. |
|
|
IH 820 near Iron Horse/Big Fossil Creek |
|
| • |
|
Construction of concrete columns and retaining walls, and the setting of beams for the new eastbound and westbound frontage roads over Big Fossil Creek. |
|
| • |
|
Note: The closure of the IH 820 westbound off-ramp to Iron Horse Dr. is expected to last until October 2012. |
|
|
IH 820 near Holiday Lane |
|
| • |
|
Continued construction of concrete columns, caps and retaining walls for the IH 820/Holiday Lane improvements.
|
|
|
SH 121/183 btwn Northeast Mall and Precinct Line Rd |
|
| • |
|
Excavation work and the installation of drainage. |
|
| • |
|
Construction of columns and retaining walls. |
|
|
SH 121/SH 183 near Hurstview Drive |
|
| • |
|
Opening of the pedestrian bridge near Hurstview Dr. in mid- to late-April. |
|
| • |
|
Continued construction of the new westbound frontage road. |
|
| • |
|
Soil work and construction of retaining walls at Norwood Dr. along the westbound SH 121/183 frontage road. |
|
| • |
|
Note: Hurstview Bridge closed on April 16, 2012 and will be closed for approximately one year. |
|
|
SH 121/SH 183 btwn Bedford Road and Central Drive |
|
| • |
|
Installation of drainage and construction beams for the new westbound lanes of SH 121/183. |
|
| • |
|
Construction of retaining walls along Central Dr. and Forest Ridge Dr. The placing of construction beams and pouring of new bridge decks will also take place in this area. |
|
| • |
|
Construction of retaining walls and the placement of construction columns near Central Dr. and Forest Ridge Dr. |
|
| • |
|
Note: The u-turns on both the eastbound and westbound SH 121/183 frontage roads at Central Drive closed on September 9, 2011 and will reopen when the bridge reconstruction is completed. |
|
| • |
|
Note: The Bedford Road off-ramp from westbound SH 121/183 is closed through early 2013. Traffic is redirected to take the previous exit at Central Drive. |
|
| • |
|
Note: The on-ramp to westbound SH 121/183 just west of Central Drive closed on August 19, 2011 and will reopen in late 2012. |
|
|
SH 121/SH 183 split near Murphy Drive / Westpark Way |
|
| • |
|
A new left-lane exit from eastbound SH121/183 to northbound SH121 opened on January 7. Drivers should be aware of the traffic shift. |
|
| • |
|
Continued placement of construction columns and beams at SH 121/183 split. |
|
| • |
|
Construction of retaining walls. |
|
| • |
|
Note: The direct connect from westbound SH 183 to northbound SH 121 is permanently closed for construction of a new connection. Traffic is being redirected to use the previous exit at Murphy Drive/Westpark Way. |
|
|